Unfortunately due to unforeseen circumstances we will need to cancel tonight’s meeting as we do not have a quorum. We will try and reschedule for next week.
Apologies
Unfortunately due to unforeseen circumstances we will need to cancel tonight’s meeting as we do not have a quorum. We will try and reschedule for next week.
Apologies
A lot of folks have been having problems getting the correct compensation from their ISPs if any at all. You should normally have received around £410.
Some may be due less if the ISP gave mobile (4G) fallback. And some may be due more if the fault lingered on.
The idea of this post is you can point your ISP to back-up your claim.
For those who did not get the correct amount of compensation the first section gives the correct dates. For those who were refused compensation because it “was out with our control” the second section quotes the “ISPs” industry’s code of conduct that forbids ISPs doing this.
This is probably because the ISP is using the wrong dates. Often the 7th to 31st Of October. They should be using the 3rd of October to 18th November. Allowing for excluded days this works out as 41 days * £9.98 = £409.18.
The correct Start date:
We have now managed to get Openreach to confirm that broadband went down when power was lost on the 3rd of October.
“When power was restored on 7th October, it was then discovered that the subsea cable was impacted which effected full fibre customers. “
It was at this point that Openreach issued an area fault to all ISPs. This is why some ISPs wrongly use the 7th of October, when they should be using the 3rd.
The correct Fix Date
Some ISPs are using the 31st of October as a fix date. This was the date that Openreach gave an update. The fix was not till the 18th of November (just before the Scotland/Denmark game). BT emergency team have now acknowledged this via Jenni Minto’s team:
“BT advise that the repair successfully concluded on 18 November 2025 and that internet service providers will have been made aware of that. On that basis I would expect that 18 November is the date that would be used to determine the level of compensation due.”
ISPs avoiding payment of automatic compensation
Some islanders have been told that no compensation is due because it was out with the ISP’s control. However, section 40 of Ofcom’s industry-code-of-practice-for-automatic-compensation states that ISPs cannot avoid compensation by saying it was not their fault.
“40. Subject to the exceptions in paragraph 39 above, the Communications Provider does not
avoid payment of automatic compensation if the issue was caused by an event outside of
the customer’s or its own control This type of event would include (but would not be limited
to) extreme weather, strikes and third-party acts.”
The document can be found here: https://www.ofcom.org.uk/siteassets/resources/documents/consultations/uncategorised/98684—automatic-compensation/associated-documents/industry-code-of-practice-for-automatic-compensation-2024-v1.pdf?v=392135
If ISPs claim the are not liable, direct them to the above document.
Meanwhile we are trying to get the ISPs to sort this out automatically as is their duty. Progress is slow.
Please find below an update from CM assets on the new Pier building and marshalling area: (Note option 1 was chosen”)
“I have provided some further information for you below that you can communicate back to the Community.
I appreciate that it is not obvious from the presentation documentation that is on the project webpage, however Option 1 was selected to take forward to the detailed design stage and is what will be built.
Please see attached the most recent general arrangement plan that formed part of the tender documentation.
Due to the scale of the construction works, the tender process was extended until after the Christmas period, with the following updated timescales:
Key project milestones
· Project tender issued: Q3 2025
· Contract awarded: Feb/Mar 2026
· Construction starts: Anticipated Spring 2026, subject to funding approval
· Construction duration: Approximately 12 months
In your response to being worried about “subject to funding approval”, due to the size and anticipated budget estimates for construction, we will still need to apply to Transport Scotland to approve funding through our business case justification process, once the tender process has been completed and we know how much the construction contract will be.”
For more info go to:
Tiree Terminal Works’ detailed design completed as tender process begins
TIREE COMMUNITY COUNCIL
JANUARY PUBLIC MEETING 7pm Wednesday 14 January 2026
Meeting will be inperson (at Trust offices), on Zoom and streamed to our Facebook account where it will remain for 30 days. We will delete our copy of the video once the minutes have been signed off.
Join Zoom Meeting
https://us06web.zoom.us/j/89225224846?pwd=DRamSWl2yRIHGCbvCcHslhGS9KrrhE.1
Meeting ID: 892 2522 4846
Passcode: jrHrb1
MINUTES TIREE COMMUNITY COUNCIL
DECEMBER PUBLIC MEETING 5pm Wednesday 10 December 2025
Conference Room, Trust Offices In person
None of these applications needed to be considered under TCC planning policy
Dr John Holliday 11 December 2025
Islands Connectivity Plan – CNA – Oban Services Survey Poster
We have been sent some links for the Island Connectivity Plan survey. We want to make sure as many people as possible get the chance to respond. This is an opportunity for islanders to have input on future island connections.
The Survey for these islands has gone live today, 10 December, and can be found at https://arcg.is/qOzez0
For further information on the Islands Connectivity Plan please see the following links :
Islands Connectivity Plan | Transport Scotland
Islands Connectivity Plan | Community Needs Assessments | Transport Scotland
Owing to a couple of things we are having to cancel this month’s TCC meeting.
Sorry
MINUTES
TIREE COMMUNITY COUNCIL
7pm 15 October 2025
An Talla and on Zoom
Dr John Holliday
17 October 2025
(Comms willing)
Please note new Zoom link
https://us06web.zoom.us/j/7935569301?pwd=qeHEdMGGKZBvGdyw7cUVUi0LV9f57z.1
Join Zoom Meeting
https://us06web.zoom.us/j/7935569301?pwd=qeHEdMGGKZBvGdyw7cUVUi0LV9f57z.1
Because of the internet problems we have mode the meeting to a hybrid mode.
Meeting will be in person and streamed to Facebook for the lucky people with internet.
We will issue a amended agenda later moving “Stormy Amy” nearer the top.
Zoom link is the same.