We have been sent a document showing the phases of the work at the calmac terminal. As with all projects of this size we assume things may change. However, the first few pages show the changes that will happen in the coming weeks. It does show some parking spaces and access to the EV chargers.
Covering email from the terminal works team:
“The contractor and our consultants are still putting the final touches to the Traffic Management Plan for the works during the various phases. There will always be a section of the existing car park that is still available for customer and CFL parking (around 12-15 spaces depending on the size of the contractor’s compound) To this end, please see attached the basis of the phasing of the project which is subject to some minor changes in the development of the TMP but is still largely as it will take place.
I will get some visuals from our consultants and pass on once received for the actual building. ”